The UK Construction funnel problem

Earlier this year I attended a conference in London where Mark Farmer of EC Harris articulated some serious concern about the volume of construction activity in the pipeline and the likely ‘blockage’ that would occur with Main Contractors and Sub-Contractors, specifically in relation to their ability to respond to market demands. The issue being a lack of resources – and materials in some cases (brick availability being a big problem).

It seems that investors and developers have funds and are pushing projects forward at pace now – some of which are large, especially in the Residential sector. However the anticipated delivery/ supply chain blockage is now being realised…

UK Construction Funnel

At present we are engaged in the development of circa 3500+ Residential dwellings in London on numerous sites. In addition, following recent instructions, we have a fairly similar figure again in the UK regions – Manchester being a particular hotspot. Our Residential team is continuing to grow with our group team nearing 130 staff in recent weeks.

Our work winning success seems to be as a result of our focused/ efficient operating model, the scale and diversity of our team experience, and our extensive use of BIM. A big strategic focus for the group is on diversification and this is working very well for us. We’ve recently been appointed on Student Living, Education, Industrial and Healthcare related projects, in addition to our existing ever growing port-folio of Residential, Retail and Leisure work.

One thing that’s fueling the surge of major projects in construction is the significant interest and activity in the emerging ‘built to rent’ or ‘private rented sector’ (PRS), to deliver large Residential products, these are funded by institutional and international funds. This is something we’re involved with at present.

Our London projects are perhaps proving the most challenging at present, in terms of Tender dialogue, as Main Contractors are needing to be very selective about what they can physically handle. Furthermore sub-contractors are struggling to respond to pre-construction programme demands in terms of finalising designs and cost plans.

So the wider impact of all this could be significant, with cost plans rising and construction programme’s becoming protracted in some cases. It’s been reported in the press over the last week or so that brick layers are earning £1000 a week now. There’s a sense of the tail waging the dog here!

This issue won’t resolve itself quickly. There is now a clear skills and resources shortage in the Construction industry which simply can’t handle the current demands of the Property and Investment sector.

There’s a real irony here of course; The Construction sector has been the worst affected by the recession, by some margin. Now the recovery has recently occurred so quickly that the sector simply can’t cope with demand. It will be interesting to see how this unfolds in the 12 months as developers and contractors race to complete projects on site.

So whilst we as architects are incredibly busy bringing new developments to market, the challenge will remain for sometime yet in terms of building these on site effectively.